Logistics centre · 2024
Rustavi
Concept visual · to be replaced with a photo of the project
4 200m²
floor area
floor area
8months
of construction
of construction
2024year
handed over
handed over
About the project
Key facts
Class A warehouse complex with loading ramps and an office block. Phase one went live 6 months after the start.
- Type
- Logistics centre
- Floor area
- 4 200 m²
- Location
- Rustavi
- Storeys
- Single storey, 12 m clear height
- Construction period
- 8 months
- Year of handover
- 2024
- Completion stage
- Ready for fit-out
- Contract price
- Unchanged
Visual direction
The look of the project
This is a concept visual for the page layout, not a photo of the completed project.
Concept
Progress
Stages
and timeline
- 01Site and utilities check — 2 weeks
- 02Design — 2 months
- 03Foundations and frame — 4 months
- 04Envelope and floors — 2 months
- 05Handover — 2 weeks
Next step
Discuss
a similar project
Tell us what you want to build — we will find a project close in type and area and price yours.