Aparthotel complex · 2022
Vake
Concept visual · to be replaced with a photo of the project
8 900m²
floor area
floor area
14months
of construction
of construction
2022year
handed over
handed over
About the project
Key facts
Aparthotel complex with 96 units and a commercial ground floor. Built on a plot sourced by our team.
- Type
- Aparthotel complex
- Floor area
- 8 900 m²
- Location
- Tbilisi
- Storeys
- 11 storeys
- Construction period
- 14 months
- Year of handover
- 2022
- Completion stage
- Ready for fit-out
- Contract price
- Unchanged
Visual direction
The look of the project
This is a concept visual for the page layout, not a photo of the completed project.
Concept
Progress
Stages
and timeline
- 01Site selection — 4 weeks
- 02Design and permits — 4 months
- 03Structural frame — 7 months
- 04Facade and utilities — 3 months
- 05Handover — 2 weeks
Next step
Discuss
a similar project
Tell us what you want to build — we will find a project close in type and area and price yours.
+995 599 538 277WhatsApp · Telegram
- 01Brief
- 02Design
- 03Estimate
- 04Lock-in